Projects · SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED
SIGNATURE GLOBAL CITY 63A
SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED · VILLAGE KADARPUR SECTOR 63
At a glance
| 1. Registration | valid up to 24/02/2027; on HRERA's registered list |
|---|---|
| 2. Completion | declared by builder: likely completion 28-02-2023; registration extended 4 times |
| 3. Occupation certificate | none on record |
| 4. HRERA's own proceedings | 2 (2 not disposed) |
| 5. Buyer complaints (decided) | 5 against SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED across all its projects (not yet linked to individual projects) |
| 6. Latest quarterly report | period ending 30/09/2026 (JUL-SEP), filed 14-Oct-2026 |
Details and sources for each line are below.
Registration
| Project name | SIGNATURE GLOBAL CITY 63A |
|---|---|
| Builder (promoter) | SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED |
| Location | VILLAGE KADARPUR SECTOR 63 |
| RERA project ID | RERA-GRG-1023-2022 |
| Registration certificate number | GGM/546/278/2022/21 DATED 31.03.2022 |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 24/02/2027 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | Extension Certificate Uploaded |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 5.0125 acres |
| Licence | 110 OF 2021 DATED 17.12.2021 |
| Estimated cost of the project | ₹11,866.8 lakh (₹118.67 crore) |
| Total units (plots, apartments, shops) | 72 |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 01-03-2022 |
| Building plans approved on | Not found in the records checked |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-03-2022 |
|---|---|
| Likely completion date | 28-02-2023 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 30/09/2026 (JUL-SEP) |
| Latest report submitted on | 14-Oct-2026 |
| Quarterly reports listed on the portal | 17 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | None found in the records checked |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration |
|
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | 2 |
|---|---|
| By status | First Hearing: 1; Pending: 1 |
| Proceedings |
Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against SIGNATUREGLOBAL (INDIA) PRIVATE LIMITED (all its projects) | 5 (Complaint: 5) |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: rera@sodham.ai