RERA Details by Sodham

Projects · Y B BUILDERS PVT LTD

NIMAI PLACE

Y B BUILDERS PVT LTD · SECTOR 114 GURUGRAM

At a glance

1. Registrationvalid up to 31/03/2023; on HRERA's registered list
2. Completiondeclared by builder: revised completion date 30-09-2020; registration extended 1 time
3. Occupation certificate2 on record, latest dated 12 Apr 2023
4. HRERA's own proceedings5 (5 not disposed)
5. Buyer complaints (decided)13 against Y B BUILDERS PVT LTD across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 31/03/2025 (JAN-MAR), filed 05-Aug-2026

Details and sources for each line are below.

Registration

Project nameNIMAI PLACE
Builder (promoter)Y B BUILDERS PVT LTD
LocationSECTOR 114 GURUGRAM
RERA project IDRERA-GRG-10-2018
Registration certificate numberGGM/275/2018/07 DATED 13.07.2018
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/03/2023
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area3.0125 acres
Licence126 of 2012
Estimated cost of the project₹16,000 lakh (₹160 crore)
Total units (plots, apartments, shops)441
Units booked when registered249
Units unsold when registered192
Layout plan approved on01-09-2014
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date01-09-2019
Revised completion date30-09-2020
Infrastructure: projected completion30-09-2020
Infrastructure: percentage complete when registered71%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/03/2025 (JAN-MAR)
Latest report submitted on05-Aug-2026
Quarterly reports listed on the portal26

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registration
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed5
By statusFirst Hearing: 2; Online Complaint Not Yet Received At Office: 1; Pending: 2
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against Y B BUILDERS PVT LTD (all its projects)13 (Complaint: 12; Compensation: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai