Projects · LEKH BUILDTECH PRIVATE LIMITED
M3M JEWEL
LEKH BUILDTECH PRIVATE LIMITED · SECTOR-25, GURUGRAM
At a glance
| 1. Registration | valid up to 30/03/2026; on HRERA's registered list |
|---|---|
| 2. Completion | declared by builder: likely completion 31-03-2026 |
| 3. Occupation certificate | 1 on record, latest dated 09 Sep 2026 |
| 4. HRERA's own proceedings | none listed |
| 5. Buyer complaints (decided) | 0 against LEKH BUILDTECH PRIVATE LIMITED across all its projects (not yet linked to individual projects) |
| 6. Latest quarterly report | period ending 31/06/2023 (APR-JUN), filed 01-Jun-2024 |
Details and sources for each line are below.
Registration
| Project name | M3M JEWEL |
|---|---|
| Builder (promoter) | LEKH BUILDTECH PRIVATE LIMITED |
| Location | SECTOR-25, GURUGRAM |
| RERA project ID | RERA-GRG-1199-2022 |
| Registration certificate number | GGM/635/367/2022/110 DATED 28.11.2022 (SUPERSEDED BY GGM/722/454/2023/66 DATED 29.05.2023) |
| Registration status | Listed on HRERA Gurugram's registered projects list |
| Registration valid up to | 30/03/2026 |
| Registered with | HRERA |
| Registration certificate | View on HRERA Gurugram |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Application on the portal
| Application status | APPROVED AND CERTIFICATE UPLOADED |
|---|
Source: HRERA Gurugram, project detail page, checked 16 Nov 2026
Project details (from the registration form, Form A-H)
| Project type | New project |
|---|---|
| Land area | 1.32068 acres |
| Licence | .is not applicable as the Promoter has purchased the land directly from HSVP |
| Estimated cost of the project | ₹35,783.96 lakh (₹357.84 crore) |
| Total units (plots, apartments, shops) | 372 |
| Units booked when registered | Not applicable (new project) |
| Units unsold when registered | Not applicable (new project) |
| Layout plan approved on | 15-11-2022 |
| Building plans approved on | 15-11-2022 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Timeline declared by the builder
| Likely start of construction | 01-12-2022 |
|---|---|
| Likely completion date | 31-03-2026 |
Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026
Quarterly progress reports
| Shown on the registered projects list | Reports listed |
|---|---|
| Latest report period | 31/06/2023 (APR-JUN) |
| Latest report submitted on | 01-Jun-2024 |
| Quarterly reports listed on the portal | 2 |
Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026
Certificates and changes
| Occupation / completion certificates (OC/CC/PCC) | |
|---|---|
| Corrigenda / addenda to the registration | None found in the records checked |
| Extensions of registration | None found in the records checked |
Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026
HRERA's own compliance proceedings on this project
Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.
| Proceedings listed | None listed on the portal |
|---|---|
| By status | None |
| Proceedings | None |
Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026
Decided buyer complaints
From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.
| Decided cases linked to this project | None linked yet (orders are being matched to projects) |
|---|---|
| Decided cases against LEKH BUILDTECH PRIVATE LIMITED (all its projects) | None in the list |
Source: HRERA Gurugram, judgements list, checked 16 Nov 2026
This is the data I have; the decision rests with you. Report an error: rera@sodham.ai