RERA Details by Sodham

Projects · SECTOR 113 GATEVIDA DEVELOPERS PRIVATE LTD

LA VIDA PHASE 2

SECTOR 113 GATEVIDA DEVELOPERS PRIVATE LTD · SECTOR 112/113 , VILLAGE BAJG HERA, GURUGRAM

At a glance

1. Registrationvalid up to 11/08/2027; on HRERA's registered list
2. Completiondeclared by builder: likely completion 31-08-2027
3. Occupation certificatenone on record
4. HRERA's own proceedingsnone listed
5. Buyer complaints (decided)13 against SECTOR 113 GATEVIDA DEVELOPERS PRIVATE LTD across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 30/09/2026 (JUL-SEP), filed 20-Oct-2026

Details and sources for each line are below.

Registration

Project nameLA VIDA PHASE 2
Builder (promoter)SECTOR 113 GATEVIDA DEVELOPERS PRIVATE LTD
LocationSECTOR 112/113 , VILLAGE BAJG HERA, GURUGRAM
RERA project IDRERA-GRG-1118-2022
Registration certificate numberGGM/639/371/2022/114 DATED 28.11.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to11/08/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area6.18 acres
Licence105 of 2011(10-12-2024), 85 of 2012(28-08-2025), 86 of 2012(28-08-2025)
Estimated cost of the project₹63,101.16 lakh (₹631.01 crore)
Total units (plots, apartments, shops)284
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on24-02-2016
Building plans approved on03-06-2016

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction13-12-2018
Likely completion date31-08-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on20-Oct-2026
Quarterly reports listed on the portal15

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against SECTOR 113 GATEVIDA DEVELOPERS PRIVATE LTD (all its projects)13 (Complaint: 13)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai