RERA Details by Sodham

Projects · NEXT GENERATION PROJECTS PVT LTD

INDIA RASHTRA

NEXT GENERATION PROJECTS PVT LTD · SECTOR 88A

At a glance

1. Registrationvalid up to 30/11/2026; on HRERA's registered list
2. Completiondeclared by builder: likely completion 30-11-2026
3. Occupation certificatenone on record
4. HRERA's own proceedingsnone listed
5. Buyer complaints (decided)0 against NEXT GENERATION PROJECTS PVT LTD across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 31/12/2025 (OCT-DEC), filed 15-Jan-2026

Details and sources for each line are below.

Registration

Project nameINDIA RASHTRA
Builder (promoter)NEXT GENERATION PROJECTS PVT LTD
LocationSECTOR 88A
RERA project IDRERA-GRG-1174-2022
Registration certificate numberGGM/631/363/2022/106 DATED 21.11.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to30/11/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area10.01875 acres
Licence144 OF 2022 DATED 28-09-2022
Estimated cost of the project₹32,286 lakh (₹322.86 crore)
Total units (plots, apartments, shops)78
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on28-09-2022
Building plans approved on30-11-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-10-2022
Likely completion date30-11-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2025 (OCT-DEC)
Latest report submitted on15-Jan-2026
Quarterly reports listed on the portal12

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against NEXT GENERATION PROJECTS PVT LTD (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai