RERA Details by Sodham

Projects · PYRAMID INFRATECH PVT LTD

IMPERIAL ESTATE

PYRAMID INFRATECH PVT LTD · SECTOR- 70 A,

At a glance

1. Registrationvalid up to 20/12/2026; on HRERA's registered list
2. Completiondeclared by builder: likely completion 20-12-2026
3. Occupation certificate1 on record, latest dated 16 Dec 2024
4. HRERA's own proceedingsnone listed
5. Buyer complaints (decided)58 against PYRAMID INFRATECH PVT LTD across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 31/12/2024 (OCT-DEC), filed 21-Jan-2025

Details and sources for each line are below.

Registration

Project nameIMPERIAL ESTATE
Builder (promoter)PYRAMID INFRATECH PVT LTD
LocationSECTOR- 70 A,
RERA project IDRERA-GRG-1046-2022
Registration certificate numberGGM/559/291/2022/34 DATED 16.05.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to20/12/2026
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.38125 acres
Licence120 OF 2021 DATED 24/12/2021
Estimated cost of the project₹8,435.46 lakh (₹84.35 crore)
Total units (plots, apartments, shops)85
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on31-12-2021
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction15-12-2022
Likely completion date20-12-2026

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2024 (OCT-DEC)
Latest report submitted on21-Jan-2025
Quarterly reports listed on the portal10

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against PYRAMID INFRATECH PVT LTD (all its projects)58 (Complaint: 56; Compensation: 2)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai