RERA Details by Sodham

Projects · BST DEVELOPERS INDIA PVT LTD

GREEN BHOOMI

BST DEVELOPERS INDIA PVT LTD · SECTOR 99A, VILLAGE GOPALPUR, TEHSIL HARSARU

At a glance

1. Registrationvalid up to 25/01/2027; on HRERA's registered list
2. Completiondeclared by builder: likely completion 25-01-2027
3. Occupation certificatenone on record
4. HRERA's own proceedings2 (1 not disposed)
5. Buyer complaints (decided)1 against BST DEVELOPERS INDIA PVT LTD across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 30/09/2025 (JUL-SEP), filed 12-Dec-2025

Details and sources for each line are below.

Registration

Project nameGREEN BHOOMI
Builder (promoter)BST DEVELOPERS INDIA PVT LTD
LocationSECTOR 99A, VILLAGE GOPALPUR, TEHSIL HARSARU
RERA project IDRERA-GRG-1211-2022
Registration certificate numberGGM/669/401/2023/13 DATED 16.01.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to25/01/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area5.6375 acres
Licence170 of 2022(22.10.2022)
Estimated cost of the project₹4,915.78 lakh (₹49.16 crore)
Total units (plots, apartments, shops)96
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on27-10-2022
Building plans approved onNot found in the records checked

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction26-01-2022
Likely completion date25-01-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2025 (JUL-SEP)
Latest report submitted on12-Dec-2025
Quarterly reports listed on the portal10

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed2
By statusPending: 1; Disposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against BST DEVELOPERS INDIA PVT LTD (all its projects)1 (Complaint: 1)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai