GODREJ ICON TOWER 4/E AND TOWER 5/F

OASIS LANDMARKS LLP · SECTOR 88A & 89A

At a glance

1. Registrationvalid up to 31/12/2029; on HRERA's registered list
2. Completiondeclared by builder: revised completion date 31-12-2029
3. Occupation certificatenone on record
4. HRERA's own proceedingsnone listed
5. Buyer complaints (decided)42 against OASIS LANDMARKS LLP across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 30/09/2026 (JUL-SEP), filed 16-Oct-2026

Details and sources for each line are below.

Registration

Project nameGODREJ ICON TOWER 4/E AND TOWER 5/F
Builder (promoter)OASIS LANDMARKS LLP
LocationSECTOR 88A & 89A
RERA project IDRERA-GRG-1224-2022
Registration certificate numberGGM/670/402/2023/14 DATED 16.01.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to31/12/2029
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeOngoing project (under construction when registered)
Land area1.424625 acres
Licence85 of 2013(10-10-2013), 151 of 2014(05-09-2014)
Estimated cost of the project₹12,660.46 lakh (₹126.6 crore)
Total units (plots, apartments, shops)127
Units booked when registered0
Units unsold when registered127
Layout plan approved on03-10-2018
Building plans approved on03-10-2018

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Earlier completion date25-01-2022
Revised completion date31-12-2029
Infrastructure: projected completion31-12-2029
Infrastructure: percentage complete when registered0%

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period30/09/2026 (JUL-SEP)
Latest report submitted on16-Oct-2026
Quarterly reports listed on the portal14

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against OASIS LANDMARKS LLP (all its projects)42 (Complaint: 37; Compensation: 2; Execution of an earlier order: 3)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026