RERA Details by Sodham

Projects · EMAAR INDIA LIMITED

EMAAR BUSINESS DISTRICT 75A

EMAAR INDIA LIMITED · VILLAGE - BEGAMPUR KHATOLA, S ECTOR 75A, GURUGRAM

At a glance

1. Registrationvalid up to 23/08/2027; on HRERA's registered list
2. Completiondeclared by builder: likely completion 23-08-2027
3. Occupation certificatenone on record
4. HRERA's own proceedings1 (0 not disposed)
5. Buyer complaints (decided)97 against EMAAR INDIA LIMITED across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 31/12/2025 (OCT-DEC), filed 13-Jan-2026

Details and sources for each line are below.

Registration

Project nameEMAAR BUSINESS DISTRICT 75A
Builder (promoter)EMAAR INDIA LIMITED
LocationVILLAGE - BEGAMPUR KHATOLA, S ECTOR 75A, GURUGRAM
RERA project IDRERA-GRG-1135-2022
Registration certificate numberGGM/690/422/2023/34 DATED 02.02.2023
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to23/08/2027
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area4.55625 acres
Licence129 of 2022
Estimated cost of the project₹8,143 lakh (₹81.43 crore)
Total units (plots, apartments, shops)55
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on25-08-2022
Building plans approved on25-08-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction24-09-2022
Likely completion date23-08-2027

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2025 (OCT-DEC)
Latest report submitted on13-Jan-2026
Quarterly reports listed on the portal11

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusDisposed: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against EMAAR INDIA LIMITED (all its projects)97 (Execution of an earlier order: 36; Complaint: 57; Compensation: 4)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai