CENTRAL PARK FLOWER VALLEY FLOORS AND VILLAS

CENTRAL PARK FLOWER VALLEY · VILLAGE DHUNELA & BERKA, SECT OR-29,30,32 AND 33, SOHNA

At a glance

1. Registrationvalid up to 31/12/2024; marked "Lapsed Project" by HRERA
2. Completiondeclared by builder: likely completion 31-12-2024
3. Occupation certificatenone on record
4. HRERA's own proceedings1 (1 not disposed)
5. Buyer complaints (decided)8 against CENTRAL PARK FLOWER VALLEY across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 31/12/2024 (OCT-DEC), filed 13-Jan-2025

Details and sources for each line are below.

Registration

Project nameCENTRAL PARK FLOWER VALLEY FLOORS AND VILLAS
Builder (promoter)CENTRAL PARK FLOWER VALLEY
LocationVILLAGE DHUNELA & BERKA, SECT OR-29,30,32 AND 33, SOHNA
RERA project IDRERA-GRG-1084-2022
Registration certificate numberGGM/624/356/2022/99 DATED 27.10.2022
Registration statusMarked "Lapsed Project" on HRERA Gurugram's registered projects list
Registration valid up to31/12/2024
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusAPPROVED AND CERTIFICATE UPLOADED

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area14.4938 acres
Licence54 of 2014, 28 of 2016 and 07 of 2020
Estimated cost of the project₹74,524.13 lakh (₹745.24 crore)
Total units (plots, apartments, shops)948
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on13-12-2021
Building plans approved on26-10-2017

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction28-08-2017
Likely completion date31-12-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2024 (OCT-DEC)
Latest report submitted on13-Jan-2025
Quarterly reports listed on the portal8

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)None found in the records checked
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registrationNone found in the records checked

Source: not checked yet

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listed1
By statusPending: 1
Proceedings

Source: HRERA Gurugram, monitoring cases for this project, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against CENTRAL PARK FLOWER VALLEY (all its projects)8 (Compensation: 8)

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026