RERA Details by Sodham

Projects · AVARNA PROJECTS LLP

BIRLA NAVYA (DRISHA 1B)

AVARNA PROJECTS LLP · SECTOR 63A GURUGRAM

At a glance

1. Registrationvalid up to 29/12/2025; on HRERA's registered list
2. Completiondeclared by builder: likely completion 31-12-2024; registration extended 1 time
3. Occupation certificate1 on record, latest dated 29 Dec 2025
4. HRERA's own proceedingsnone listed
5. Buyer complaints (decided)0 against AVARNA PROJECTS LLP across all its projects (not yet linked to individual projects)
6. Latest quarterly reportperiod ending 31/12/2025 (OCT-DEC), filed 15-Jan-2026

Details and sources for each line are below.

Registration

Project nameBIRLA NAVYA (DRISHA 1B)
Builder (promoter)AVARNA PROJECTS LLP
LocationSECTOR 63A GURUGRAM
RERA project IDRERA-GRG-1011-2022
Registration certificate numberGGM/553/285/2022/28 DATED 25.04.2022
Registration statusListed on HRERA Gurugram's registered projects list
Registration valid up to29/12/2025
Registered withHRERA
Registration certificateView on HRERA Gurugram

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Application on the portal

Application statusExtension Certificate Uploaded

Source: HRERA Gurugram, project detail page, checked 16 Nov 2026

Project details (from the registration form, Form A-H)

Project typeNew project
Land area2908.1 acres
LicenceNA
Estimated cost of the project₹6,803 lakh (₹68.03 crore)
Total units (plots, apartments, shops)55
Units booked when registeredNot applicable (new project)
Units unsold when registeredNot applicable (new project)
Layout plan approved on07-09-2019
Building plans approved on17-01-2022

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Timeline declared by the builder

Likely start of construction01-12-2021
Likely completion date31-12-2024

Source: HRERA Gurugram, registration form (Form A-H), checked 16 Nov 2026

Quarterly progress reports

Shown on the registered projects listReports listed
Latest report period31/12/2025 (OCT-DEC)
Latest report submitted on15-Jan-2026
Quarterly reports listed on the portal14

Source: HRERA Gurugram, latest quarterly progress report, checked 16 Nov 2026

Certificates and changes

Occupation / completion certificates (OC/CC/PCC)
Corrigenda / addenda to the registrationNone found in the records checked
Extensions of registration

Source: HRERA Gurugram, "View OC/CC/PCC" and "View Corrigendum", checked 16 Nov 2026

HRERA's own compliance proceedings on this project

Cases the Authority started itself, for example for a missed quarterly report or an expired registration. These are not complaints by buyers.

Proceedings listedNone listed on the portal
By statusNone
ProceedingsNone

Source: HRERA Gurugram, registered projects list, checked 16 Nov 2026

Decided buyer complaints

From HRERA Gurugram's list of decided cases (complaints, compensation and execution). Pending complaints can only be searched on the portal one by one behind a CAPTCHA, so they are not included. Complainants' names are not shown.

Decided cases linked to this projectNone linked yet (orders are being matched to projects)
Decided cases against AVARNA PROJECTS LLP (all its projects)None in the list

Source: HRERA Gurugram, judgements list, checked 16 Nov 2026

This is the data I have; the decision rests with you. Report an error: rera@sodham.ai